Much of the six-lane Rajiv Gandhi Salai (OMR) is under a foot deep water after sharp shower because it lacks a proper stormwater drainage system.
The Hindu, in a Page 2 article by Deepa H Ramakrishnan, says: "Though the detailed project report of the road had proposed construction of drains to carry stormwater, this was not implemented. The Tamil Nadu Road Development Company (TNRDC) gave it up and the State government said that local bodies would construct the drains.
"The road was constructed at a cost of Rs. 400 crore and the average collection from the toll plazas touches Rs. 3 crore per month. TNRDC also gets income from advertising revenue. The drains would cost just Rs. 15 crore, but according to sources, the company did not have adequate funding to construct them.
"Though the road became a tolled facility in December 2008, construction of footpaths and ducts has yet to be completed. The road also does not have bus shelters...
Source: A 'world-class' road, a horror in a downpour
The Hindu, in a Page 2 article by Deepa H Ramakrishnan, says: "Though the detailed project report of the road had proposed construction of drains to carry stormwater, this was not implemented. The Tamil Nadu Road Development Company (TNRDC) gave it up and the State government said that local bodies would construct the drains.
"The road was constructed at a cost of Rs. 400 crore and the average collection from the toll plazas touches Rs. 3 crore per month. TNRDC also gets income from advertising revenue. The drains would cost just Rs. 15 crore, but according to sources, the company did not have adequate funding to construct them.
"Though the road became a tolled facility in December 2008, construction of footpaths and ducts has yet to be completed. The road also does not have bus shelters...
Source: A 'world-class' road, a horror in a downpour